Manufacturing process


Curing



Upon casting the concrete elements are covered with a tarpaulin in order that the moisture is retained and there is no exposure to any dry winds. The covered pallets are transported to custom-built curing chambers.

The pallets are then left covered for 8 to 14 hours in order to ensure that the minimum design strength of 15 N/mm2 is obtained before progressing to demoulding.